TfL recorded 609 reliability complaints about routes from the north London depot and says work with Go-Ahead has since improved services
Go-Ahead London’s Northumberland Park bus garage was placed on an improvement plan after Transport for London (TfL) raised concerns about the reliability of services operating from the depot.
In a Freedom of Information response published on 29 October, TfL said it received 609 reliability complaints about routes operating from the garage between 1 April and 16 October 2026.
In a statement to London Bus Forums News, TfL said significant work had been carried out with the operator to improve performance.
“The measures introduced have resulted in improvements in service performance,” a TfL spokesperson said, adding that the authority would continue monitoring progress.
TfL previously described route 91, which runs between Wood Green and Trafalgar Square, as a “long-term poor performer”, with reliability concerns continuing despite additional buses being introduced.

Image: Samuel Letsu
However, the authority said London General’s overall performance had generally been satisfactory, with improvements recorded at Northumberland Park following its intervention.
Go-Ahead London has meanwhile retained the contract to operate routes 91 and N91 for a further four years through its London General subsidiary, following a tender process that attracted two bids.
TfL’s tender results show London General submitted the successful bid of £8.72 million a year, equivalent to around £34.9 million over four years at the published annual rate.
Separately, TfL said a temporary reliability scheme on route 91 would be withdrawn when the new contract begins in January 2027, with additional buses provided under the agreement.
The route will then return to operating six buses an hour.
Go-Ahead London did not respond to a request for comment.